During the option period we chose to have the sewer lines scoped with a camera and knew going into this that there was a belly (low spot) in the sewer line underneath the master and second bedrooms that had been holding water and sediment and would need to be repaired. Knowing the plumbing was going to have to be addressed anyway played a big part in the decision to go ahead with the major bedroom suite remodel. With the plumber was scheduled for late this week, the guys started with the concrete demo.
|
Saw cutting the slab in preparation for the jack hammering |
|
Roughly where we believe the lowest point is so a test opening so we can assess the extent of the deterioration. |
We also discovered that the floor slab is thin, probably only 3" and the welded wire mesh reinforcement is laying below the concrete slab. Welded wire mesh should be supported just like reinforcement bars, but it is frequently "pulled up" or "walked in" to poured concrete. Neither method is recommended because it will end up at the bottom of the concrete and serving no purpose what so ever. OK I will get off this soap box for now. I am sure I will find more things to rant about as we go along.
|
Existing sewer pipe approximately 16" down from the top of slab |
|
So much for the floor slab. Here they have both exposed the existing pipe and are creating the paths for the new plumbing to be placed. |
|
View from the new bathroom looking back into the office. |
While the guys labored away in the house with the concrete, I have been having a bout of indecision-itis. It took numerous trips to Home Depot, and more red/red-orange paint samples than you see here, we have finally come to a decision on the exterior paint colors. I think... The painter doesn't come until this weekend, so I may still change my mind. All this for the door color, I may never select wall colors.
|
Indecision Central |